ISACA IT-Risk-Fundamentals Dumps - Try Free IT-Risk-Fundamentals Exam Questions and Answer
DOWNLOAD the newest ExamcollectionPass IT-Risk-Fundamentals PDF dumps from Cloud Storage for free: https://drive.google.com/open?id=1JSBfucVS_9C71Ha6I6lhvhDDsvYZO3fU
The moment you choose to go with our IT-Risk-Fundamentals study materials, your dream will be more clearly presented to you. Next, through my introduction, I hope you can have a deeper understanding of our IT-Risk-Fundamentals learning quiz. We really hope that our IT-Risk-Fundamentals Practice Engine will give you some help. In fact, our IT-Risk-Fundamentals exam questions have helped tens of thousands of our customers successfully achieve their certification.
ISACA IT-Risk-Fundamentals Exam Syllabus Topics:
Topic
Details
Topic 1
Topic 2
Topic 3
Topic 4
Topic 5
>> IT-Risk-Fundamentals New Real Test <<
Latest IT-Risk-Fundamentals Exam Cram & Reasonable IT-Risk-Fundamentals Exam Price
There are many merits of our product on many aspects and we can guarantee the quality of our IT-Risk-Fundamentals practice engine. Firstly, our experienced expert team compile them elaborately based on the real exam. Secondly, both the language and the content of our IT-Risk-Fundamentals study materials are simple. The content emphasizes the focus and seizes the key to use refined IT-Risk-Fundamentals Questions and answers to let the learners master the most important information by using the least practic. Three, we provide varied functions to help the learners learn our study materials and prepare for the exam.
ISACA IT Risk Fundamentals Certificate Exam Sample Questions (Q37-Q42):
NEW QUESTION # 37
Which of the following is the PRIMARY reason to conduct a cost-benefit analysis as part of a risk response business case?
Answer: C
Explanation:
The primary reason for a cost-benefit analysis in a risk response business case is to determine whether the reduction in risk achieved by the response justifies the cost of implementing it. It's about weighing the potential benefits (reduced risk) against the costs of the response.
While determining future resource requirements (B) and calculating ROI (C) can be part of the analysis, the primary focus is on justifying the cost based on risk reduction.
NEW QUESTION # 38
The MOST important reason for developing and monitoring key risk indicators (KRIs) is that they provide:
Answer: A
Explanation:
Step by Step Comprehensive Detailed Explanation with All References:
* Purpose of KRIs:
* KRIs are designed to provide early warnings about potential risk events.
* They help organizations to take preventive actions before risks become critical issues.
* Early Warning System:
* KRIs are critical for proactive risk management, enabling organizations to respond quickly to changes in risk levels.
* They complement other risk management tools by focusing on early detection.
* References:
* ISA 315 (Revised 2019), Anlage 5discusses the importance of timely and accurate information in managing and mitigating risks effectively.
NEW QUESTION # 39
Which of the following is the MOST important information for determining the critical path of a project?
Answer: C
Explanation:
Project Management Context:
* Thecritical pathin project management is the sequence of stages determining the minimum time needed for an operation.
Factors Affecting the Critical Path:
* Regulatory requirementsare essential but typically do not define the sequence of tasks.
* Cost-benefit analysisinforms decision-making but does not directly determine task dependencies or timings.
* Specified end datesdirectly impact the scheduling and dependencies of tasks, defining the critical path to ensure project completion on time.
Conclusion:
* Specified end datesare the most critical information for determining the critical path, as they establish the framework within which all tasks must be completed, ensuring the project adheres to its schedule.
NEW QUESTION # 40
Incomplete or inaccurate data may result in:
Answer: C
Explanation:
Incomplete or inaccurate data results in integrity risk. Here's a detailed explanation:
* Availability Risk: This pertains to the accessibility of data and systems. It ensures that data and systems are available for use when needed. Incomplete or inaccurate data doesn't necessarily impact the availability but rather the quality of the data.
* Relevance Risk: This involves the appropriateness of the data for a specific purpose. While incomplete or inaccurate data might affect relevance, it primarily impacts the data's trustworthiness and correctness.
* Integrity Risk: This is directly concerned with the accuracy and completeness of data. Integrity risk arises when data is incomplete or inaccurate, leading to potential errors in processing, decision-making, and reporting. Ensuring data integrity means ensuring that the data is both accurate and complete.
Therefore, the primary risk associated with incomplete or inaccurate data is integrity risk.
NEW QUESTION # 41
An enterprise's risk policy should be aligned with its:
Answer: C
Explanation:
An enterprise's risk policy should be aligned with its risk appetite, which defines the amount and type of risk the organization is willing to accept in pursuit of its objectives. This alignment ensures that the risk management efforts are consistent with the strategic goals and risk tolerance levels setby the organization's leadership. Risk appetite provides a clear boundary for risk-taking activities and helps in making informed decisions about which risks to accept, mitigate, transfer, or avoid. Aligning the risk policy with the risk appetite ensures that risk management practices are in harmony with the organization's overall strategy and objectives, as recommended by frameworks like COSO ERM and ISO 31000.
NEW QUESTION # 42
......
The biggest advantage of our IT-Risk-Fundamentals study question to stand the test of time and the market is that our sincere and warm service. To help examinee to pass IT-Risk-Fundamentals exam, we are establishing a perfect product and service system between us. We can supply right and satisfactory IT-Risk-Fundamentals exam questions you will enjoy the corresponding product and service. We can’t say we are the absolutely 100% good, but we are doing our best to service every customer. Only in this way can we keep our customers and be long-term cooperative partners. Looking forwarding to your IT-Risk-Fundamentals Test Guide use try!
Latest IT-Risk-Fundamentals Exam Cram: https://www.examcollectionpass.com/ISACA/IT-Risk-Fundamentals-practice-exam-dumps.html
DOWNLOAD the newest ExamcollectionPass IT-Risk-Fundamentals PDF dumps from Cloud Storage for free: https://drive.google.com/open?id=1JSBfucVS_9C71Ha6I6lhvhDDsvYZO3fU